Sample takeoff
Download a real output from our takeoff engine: an Excel workbook and a PDF report made from a synthetic two-sheet mechanical set. It shows the Evidence sheet, the GREEN, YELLOW and RED reconciliation and the scope flags you get with every count takeoff.
Download the sample
Three files: the synthetic drawings the engine read, the Excel takeoff it produced and the PDF summary report. They are unreviewed engine output, so the status says DRAFT. That is what you would see before our review, which is the honest way to show the method.
The set is small on purpose: one schedule sheet (M501) and one level 2 mechanical plan (M201). It was built to test the engine, so it contains the problems real sets have: a TYP callout with no count, a terminal unit that is not on any schedule, and notes about an addendum and equipment replacement.
What each sheet in the workbook shows
Summary
The document status, the totals, how many lines are GREEN, YELLOW and RED, warnings about sheets that could not be read, the input file name and its SHA-256 fingerprint, the engine version and when the set was analysed. In the sample the status reads "DRAFT: 1 red row(s) have no reviewer quantity".
Takeoff
One line per tag: status, category, tag, description, schedule quantity, plan count, TYP flags, suggested quantity, reviewer quantity, final quantity, the sheets it appears on and the reason for the status. In the sample, SD-1 and RG-1 are GREEN (6 and 3, schedule and plans agree), EG-1 is YELLOW (schedule 2, plans 1, with a TYP callout that has no count) and VAV-2-04 is RED (on the plans, on no schedule).
Evidence
One row for every item found: tag, sheet, PDF page, X and Y position on the page, multiplier, whether it was counted, TYP flag, airflow, and whether it came from a callout or a note. Counted rows add up to the plan count for that tag, so every number can be traced to a place on a drawing. A note that mentions RTU-1 is listed but not counted.
By category
Totals by category, such as supply outlets, return inlets, exhaust inlets, terminal units, rooftop units and fans, with the spec section for each (MasterFormat Division 23 and the older Division 15) and whether it is counted per callout or per unit.
Scope flags
Notes found on the drawings that change the scope, with severity, sheet and the text. The sample has three: an addendum referenced, equipment replacement, and existing distribution to remain.
Sheet index
Every page in the set, its sheet number and how it was treated: mechanical or not, plan or schedule, and whether the text could be read directly.
The PDF report
The report puts the same takeoff on two pages: the status, the headline totals, a summary by category, the grouped takeoff with each line's status and reason, the scope flags and the sheet index. It is meant for the person who signs off on the bid and does not want to open a spreadsheet. The cover repeats the document status in the same words as the workbook, so a draft can never be mistaken for a reviewed takeoff.
What the sample does not show
The sample is a count takeoff. Measured trades (duct by length, piping, plumbing, electrical and drywall) are measured in Bluebeam by an estimator and delivered in Excel by item, size and unit, with the Bluebeam markup PDF. For count takeoffs, the engine does not produce a marked-up copy of the drawings with each item highlighted; the Evidence sheet gives the sheet, page and location of every counted item instead.
A delivered takeoff is reviewed by a person: red lines get a reviewer quantity and a note, and the status changes from DRAFT. The sample is left unreviewed so you can see what the engine flags on its own.
Check the sample in five minutes
The point of the Evidence sheet is that you do not have to trust us. Try it on the sample:
- Open the Excel takeoff and go to the Takeoff tab. Note that SD-1 has a plan count of 6.
- Go to the Evidence tab and filter the Tag column to SD-1. There are six rows marked Counted = yes, all on sheet M201, PDF page 2.
- Open the sample drawings and go to page 2. The X and Y values are measured in points from the top left corner of the page, so each row points to one SD-1 callout.
- Back on the Takeoff tab, look at EG-1. The schedule says 2, the plans show 1 with a TYP note, and the reason column says so. That is the line a reviewer would check first.
- Look at VAV-2-04. It is on the plan and on no schedule. It could be an addendum item, another trade's unit or a drafting error: a good RFI.
That is the same check you can run on any takeoff we deliver, on any line, before you put a number in your bid.
Pricing
- Count takeoff (air devices and equipment, for TAB and HVAC): from $245 up to 10 sheets, then $20 per sheet.
- Measured trade takeoff (duct, piping, plumbing, electrical, drywall): from $325 per trade up to 6 sheets, then $52 per sheet.
- Takeoff plus pricing with your own rates: from +$195.
Turnaround is 3 to 7 business days from payment. Emergency turnaround on request when capacity allows: $150 or 50% of the takeoff price, whichever is more.
Sample takeoff questions
Is this a real project?
No. The sample was made by our takeoff engine from a synthetic test set built for testing. It is not a client job and not a real permit set, so it can be shared freely.
Why is the sample marked DRAFT?
Because it is unreviewed engine output and one line is RED. A delivered takeoff is reviewed by a person first, and the status changes once every red line has a reviewed quantity.
Will my takeoff look the same?
Count takeoffs of air devices and equipment use the same workbook and report. Measured trades are delivered in Excel by item, size and unit, with the Bluebeam markup PDF. If you upload your own template, the quantities are laid out in it.
Does the sample include a marked-up PDF of the drawings?
No. The sample is a count takeoff, and each counted item is located on the Evidence sheet by sheet, page and position on the page. The sample drawings are included so you can check them yourself. Measured trade takeoffs do include the Bluebeam markup PDF.
Can you do a free sample on one of my jobs?
No. There is no free work on client jobs. The sample here shows the format, and a count takeoff starts at $245 for up to 10 sheets.
Which software opens the files?
The workbook opens in Excel, Google Sheets or LibreOffice. The report and the drawings are ordinary PDF files.
Request a takeoff
Send the drawings and the scope. You get a fixed quote, usually within 1 business day, and nothing starts until you accept it and pay.